Round Up Once, for the Whole Job
A 12 in. tube 4 ft long holds 3.14 cu ft of concrete. An 80 lb bag of Quikrete makes 0.60 cu ft, so each tube takes 5.24 bags. Most charts round that up for every tube, which is why Sonoco’s Builder’s Tube table lists 6 bags of 80 lb for that size. For six deck piers that becomes 36 bags.
Add the six tubes up first and the job is 18.85 cu ft, 31.4 bags, so 32 would do with nothing spare, and 33 leaves 5% for spills and an uneven hole bottom. That is three fewer bags to carry, mix and pay for. Rounding per hole only makes sense if each hole gets its own wheelbarrow load and nothing carries over. If you mix in a barrow or a small mixer and walk the leftover to the next hole, round once for the job. The calculator does that by default and shows the per-hole figure beside it; switch to “For each hole” if you’d rather never run short mid-pour.
Bag size changes the count but not the weight you lift in total. The same six piers take 44 bags of 60 lb instead of 33 of 80 lb, because a 60 lb bag makes 0.45 cu ft. That is 2,640 lb against 2,640 lb of dry mix. Lighter bags are easier to pour into a barrow on your own; heavier ones mean fewer trips from the car.
The Bag Charts Don’t Agree
Search for a 12 in. × 4 ft tube in 60 lb bags and you’ll find three answers. Quikrete’s own Quik-Tube data sheet says 7. Sonoco’s brochure gives 2 per foot, which is 8. A Quikrete project sheet hosted for Lowe’s gives 1⅓ per foot, which is 5.3 bags. The geometry says 6.98, so 7 is right, 8 has a bag spare, and the 5.3 figure would leave you more than a bag short on every tube. Chart cells are rounded by hand; the calculator works from the volume and the yield printed on the bag, so every size and length gets the same treatment, including the odd ones charts skip.
Check the Real Diameter
Tube sizes are names, not always measurements. Lowe’s lists Quikrete’s “12 in.” Quik-Tube with an actual diameter of 11.5 in. Half an inch sounds like nothing, but volume goes with the square of the diameter, so an 11.5 in. tube holds about 8% less. For the six-pier deck that is 31 bags instead of 33. If the label says “common” or gives two figures, measure inside the tube and pick “Other size”.
The Tube Is the Pier, Not the Footing
A tube gives you a neat column, but the load still has to spread into the soil at the bottom. The American Wood Council’s deck guide, DCA 6, sizes footings by the deck area each one carries, and JLC notes its newer edition raised the minimum footing diameter to 18 in., up from 15. JLC points out that builders used to 8 to 12 in. piers may be surprised by it. A bell at the bottom of the hole is one way to get that width without a wider tube all the way up.
Bigfoot forms are the usual way to get one: a plastic bell set at the bottom of the hole with the tube on top, poured in one go. They hold a lot of concrete. The BF20 takes 1.75 cu ft, the BF24 2.5, the BF36 6, and the BF28 is listed at 3.5 cu ft by Lowe’s and 3.25 by other stores, so the calculator uses 3.5. One BF28 under a 10 in. × 4 ft tube needs 10 bags of 80 lb, more than two tubes on their own. The calculator also checks the tube fits the form (a BF28 takes 10 or 12 in. tubes) and handles a poured round or square pad if you dig one instead. It counts the concrete for the footing you choose; it doesn’t work out whether that footing is big enough for your deck, which depends on spans and soil.
Depth, Height and Tube Length
The building code puts the bottom of an exterior footing at least 12 in. below undisturbed ground, and deeper where the ground freezes, down to your local frost depth. Fill or freshly dug soil doesn’t count toward that depth. Some local rules also set a height above ground; Sedgwick County in Kansas, for example, amends DCA 6 to ask for 6 in. above finished grade. Enter the whole poured length, below and above grade, as the tube length.
DIY tubes come in 4 ft lengths, and contractor tubes in 8 and 12 ft. Set the stock length under “Footing, bags and prices” and the calculator counts the tubes to buy: three 4 ft piers come out of each 12 ft tube with nothing left, while 5 ft piers get two per tube and a 2 ft offcut. A pier longer than the tube you can buy is better cut from longer stock than joined. Quikrete’s instructions call for digging the hole twice the tube’s diameter, so leave room for that when you mark out.
Sonotube Concrete Questions
Volumes are plain cylinder geometry; bag yields are Quikrete’s, Bigfoot volumes are from the retailer listings below, and the footing and depth rules from the IRC, DCA 6 and JLC. We test the engine on the worked examples above and on more than 900,000 combinations of tube size, length, pier count, footing, spare and stock length.
- Quikrete: QUIK-TUBE data sheet (bags per tube)
- Quikrete: QUIK-TUBE pillar foundations (bag yields per cu ft)
- Quikrete for Lowe’s: bags needed per foot of form height
- Sonoco: Builder’s Tube (bags for 4 ft of tube)
- Sonoco: Builder’s Tube brochure (cu ft and bags per foot)
- Lowe’s: Quikrete 12 in. tube, 11.5 in. actual
- Lowe’s: Bigfoot BF28 footing form (3.5 cu ft)
- IHL Canada: Bigfoot BF28 (3.25 cu ft)
- Home Hardware: Bigfoot BF20 (1.75 cu ft, 30 kg bag yield)
- Home Hardware: Bigfoot BF24 (2.5 cu ft)
- Kent: Bigfoot BF36 (6 cu ft, 12 to 18 in. tubes)
- JLC: DCA 6 update (18 in. minimum footing)
- JLC: better deck piers (pier weight)
- Deck footing requirements: IRC R403.1.4, 12 in. below undisturbed ground
- Sedgwick County: DCA 6 amendments (6 in. above grade)
Written and checked by Kris Lynch. Not reviewed by a licensed professional. See our methodology. Spotted a problem? Tell us. Updates: Nov 2026, launched.